Project Deliverables

  1. Implement a globally aligned finance and finance control system (global P/L structure, operator productivity measures and KPI’s, profit / cost center structure, intercompany invoicing and accounting scheme

  2. Implement a centralized and standardized approach to manage and close the file ledgers and volume statistics (e.g., kg, TEU, cbm) for the freight forwarding business

  3. Implement an Operations Control Dashboard for the freight forwarding business

  4. Implement an accurate file-based profit-sharing system for the international freight forwarding busines

Global Deployment Team

Operations Control Dashboard (OCD)

SEKO Launched the Operations Control Dashboard (OCD) July 5 ,2023 All global operators should have access to the OCD and utilize this daily to monitor exceptions. If you need access to the OCD contact your regional corporate sponsor

Click Here to Access the Operations Control Dashboard

Check out this short 3 minute video on how to navigate and use the OCD

ocd_dashboard (Original).mp4

Late Billing Metrics

SEKO went live on July 5th with Late Billing KPIs. Late billing logic is strictly looking for the 1st Accounts Receivable billing invoice/sales invoice to be issued. Once that is issued the job will fall off the late billing dashboard. For files that are cost only and no receivable invoice will be issued, operators must put in a profit and loss reason code against the job in order for the job to fall off the dashboard. For BCN files, the dashboard is looking strictly at the ASM shipment type lead master file for the receivable invoice. If the BCN files are entered properly the sub jobs will not appear on the dashboard.

Direction & Product

Trigger 1

Trigger 2

Trigger 3

Fall Back

Ground

Actual Delivered Date + 3 Days

 

 

Job Open +30 Days

Air Export

Actual Departure + 2 Days 

 

 

Job Open +30 Days

Air Import

Actual Delivered Date + 3 Days

Estimated Arrival + 5 Days

 

Job Open +30 Days

Air Cross Trade

Actual Delivered Date + 3 Days

Estimated Arrival + 5 Days

 

Job Open +30 Days

Ocean Export

Actual Departure + 3 Days

ETD + 7 Days

 

Job Open +30 Days

Ocean Import

Actual Delivered Date + 3 Days

Estimated Arrival + 10 Days

Actual Departure + 60 Days

Job Open +75 Days

Ocean Cross Trade 

Actual Delivered Date + 3 Days

Estimated Arrival + 10 Days

Actual Departure + 60 Days

Job Open +75 Days

Brokerage

Customs Cleared + 7 Days

Actual Arrival + 10 Days

 

Job Open +60 Days

Contract Logistics

 

 

 

Month End + 5 Days

Periodic Invoicing

Agreed Configuration Date set up in ORG Profile

 

 

 

None of the Above 

 

 

 

Job Open +30 Days

Gross Profit (GP) Accuracy Metrics

SEKO went live with GP Accuracy on September 11th 2023 With Phase 1 & 2

Phase

Exception

Logic

Trigger Days

Trigger Event

1

Aged Recognized WIP
MEASURE IS +30 DAYS FROM Target Billing Date

Shipments with recognized WIP  older than X days 

  1. WHEN THE USER AS A WIP (A SALES INVOICE)

  2. JOB IS RECOGNISED

30

30 days from target billing date

1

Aged Unrecognized Costs

Shipments with unrecognized costs older than X days

90

Date of CST posting

1

Negative Margin

Where GP < 0 & NO PNL reason code

 

Upon marking job CMP

2

Aged WHL/ IHL Status

Shipments that have a job status of WHL/IHL for more than 90 days

90

Job Status change date

2

Aged Non Complete Jobs

Jobs in a working status WRK , 30 days AFTER Target Billing Date
includes Status - CUS, INV, RDD, JRA , JRB , JRC

Refer On time Billing per product/ mode + 30 days from target billing date

 

2

Aged Unclosed

Job not in CLS ,JRC, IHL AND WHL , status  date present 240 days, after Target billing date 

240

From Target Billing date

2

Job Dept Error

Will provide the correct department in separate Column

 

Job Dept Auto Defaults - Based on Job Type, Mode, Directions (Service Level required for International Parcel) KPI is providing the Flag and the "Correct dept" as another column. All jobs opened up to July 2023, have been bulk updated for errors. After July 2023 errors must be manually corrected

2

Financial Closure

Shows all jobs which are status JFC, which is 30 days prior to Auto Closure to CLS

30 days prior to auto closure

Shows all jobs which are status JFC to review open WIPS & Accruals

2

Excessive Margin 

Shipments with a margin above 50% , in combination with Job Status  & NO PNL Reason Code

50%

GP % = REV + WIP + CST + ACR)// (REV + WIP)

How to Fix GP Accuracy Errors

Click here to view how to fix GP Accuracy Errors

Lightspeed Roadmap

Recorded Training Webinars & Documents

Topic

Webinar Date

Video

Operations Control Dashboard Kick Off Late Billing

June 28th, 2023

ocd_dashboard (Original).mp4

Operations Control Dashboard GP Accuracy Power Point Training

September 13, 2023

GP Accuracy Webinar Recording

Message from Steen Global Operational Excellence

October 17th, 2023

Message from Steen Global Operational Excellence

  • No labels